An empty meeting room seen from the back, rows of dark padded chairs facing a long raised wooden dais with a row of empty black chairs and slim microphones behind it, tall windows at the left showing bare trees against an evening sky, pendant ceiling lights, a wooden side desk and a dark switched-off screen on the right wall.

The Week Ahead

Effingham Weighs a Pause That Spares Camellia

On Tuesday Georgia’s Effingham County takes up OpenAI’s Project Camellia site plan and a data-center moratorium until as late as May 3, 2027, that exempts Camellia by name.

Effingham County’s commissioners are to take up two things at 6 p.m. on Tuesday: the site plan for Project Camellia, OpenAI’s planned data-center campus, and a pause on new data-center applications that exempts Camellia by name. Both are on the board’s tentative agenda, so either could still move.

The draft resolution would stop the county accepting rezonings, special- and conditional-use permit applications and variances for data centers until as late as May 3, 2027. It exempts the land deeded to Octans GA LLC, Camellia’s applicant, because the project “has been approved for zoning and development and is, therefore, a lawfully-vested use.”Resolution No. 026-038The pause ends when the county amends its zoning ordinance, when the board votes to abandon the effort, or at the close of business on May 3, 2027, whichever comes first. Applications made before it takes effect are not covered.

The county would pause new data-center applications while exempting Camellia, which has drawn two lawsuits. The resolution calls Camellia’s use vested; three residents are challenging in court an ordinance the commissioners approved on Aug. 4 that, WTOC reported, opened land already zoned industrial to data centers. They asked a judge in September to declare it invalid, and the defendants have moved to dismiss.

OpenAI calls Camellia “a long-term datacenter project that OpenAI is designing and developing in Effingham County,” for which it is contracting with Georgia Power for 3.2 gigawatts, delivered in phases between 2028 and 2032. It says it “will pay the full cost of the infrastructure and electric-service costs required to serve it.” The county’s staff report describes six data-center buildings, each about 42 feet tall, on parcels of about 740 and 607 acres, with three electrical substations and 1,608 parking spaces. Savannah expects to supply the first phase’s water “only briefly,” until a new county treatment plant comes online in early 2030, according to the regional review quoted in the staff report. The commissioners discuss a proposed county water treatment plant and intake at a 4 p.m. work session on Tuesday.

Why It Waited

The board postponed the site plan on Nov. 3 “due to lack of a firm sight and sound berm,” according to the draft minutes of that meeting, which are up for approval on Tuesday. The developer’s consultant told the board the plan was about 3 to 4 million square feet across six buildings, against about 15 million across roughly 30 in an earlier master plan, with domestic water demand of 30,000 gallons a day rather than 100,000, the minutes record.

Commissioners wanted firm answers on wetlands and written assurances of a 20-foot berm along Hodgeville Road, WTOC reported. The staff report in Tuesday’s packet does not mention a berm. The same evening brings a first reading of a change to the county’s table of permitted uses that, by the staff report’s summary, would mark data centers “C” in two industrial districts, I-1 and HI.Conditional UseThe draft minutes of Nov. 3 record Commissioner Elizabeth Helmly as having noted “that a data center moratorium and related conditional-use discussions are expected on November 17.”

The Lawsuits

The same three residents filed a second suit on Nov. 6, in Effingham County State Court, seeking damages from OpenAI OpCo LLC, Octans GA LLC, all six commissioners and the county’s industrial development authority, among others, WTOC reported. Its 11 counts include fraudulent concealment, civil conspiracy and violation of Georgia’s racketeering law. The plaintiffs allege an effort to keep the project from residents “until the land was committed and their objections could no longer matter.” None of it has been proven in court.

“The Effingham County Board of Commissioners does not comment on ongoing or pending litigation,” a spokesperson told WTOC; county leaders had repeatedly denied the claims, the station reported, and OpenAI and the authority had not responded as of its Nov. 9 report. The complaint alleges that the authority’s chief executive signed a nondisclosure agreement with OpenAI on Oct. 27, 2025, WTOC reported. OpenAI says it voided its nondisclosure agreements in Effingham in July and will not require a public official to sign one, save in narrow cases.

The Rest of the Week

On Monday evening, after a 5:30 p.m. confirmation vote, the Senate votes on cutting off debate on Sen. Shelley Moore Capito’s substitute for H.R. 2347, the bill that would make data centers pay for their grid upgrades; it needs 60 votes.

On Wednesday at 9 a.m. Central, Louisiana’s Public Service Commission meets in Baton Rouge. Neither its revised agenda, posted Nov. 10, nor its supplemental one, posted Friday, lists Meta’s Hyperion data center or the seven gas plants Entergy Louisiana wants to build to power it. Entergy will seek their approval at the commission’s Dec. 10 meeting, WWNO reported on Nov. 9, under a fast-track pathway that landowners sued that day to overturn.The Lightning DirectiveThe commission adopted the pathway 4–1 on Dec. 17, 2025, WWNO reported. It sets a commission vote within eight months of an application. The agenda does carry a “possible vote on Proposed Final Rule” on “private use electrical networks in order to enable generation to serve new large loads looking to locate in Louisiana.”

PJM’s capacity auction for 2029–30 opens Dec. 9. Its market monitor wrote last week that PJM’s delay of a separate procurement for data centers “effectively ensures that the auction will clear at the maximum price and add another $5 to $10 billion of data center related costs to all customers.” “Tech giants chasing the infinite promise of AI are finding themselves increasingly on the hook for something far earthier — the electrical grid,” Bloomberg wrote on Saturday, after an election in which voters “backed Democrats from Ohio to Texas who pledged to shield households from data centers’ insatiable electricity demands.”

Daily Cortex is written with AI models, including Anthropic’s Claude, and fact-checked with OpenAI’s GPT models.

Sources

  1. Effingham County Board of Commissioners, “(Tentative) Board of Commissioners Regular Meeting Agenda, November 17, 2026, 5:00 PM,” Nov. 2026.
  2. Effingham County Board of Commissioners, “Agenda packet, Nov. 17, 2026: draft Resolution No. 026-038 and staff report; Project Camellia staff report (Site-26-6); Permitted Use Table staff report; draft minutes of Nov. 3, 2026,” Nov. 2026.
  3. Effingham County Board of Commissioners, “(Tentative) Board of Commissioners Work Session Agenda, November 17, 2026, 4:00 PM,” Nov. 2026.
  4. OpenAI, “Building AI infrastructure with the Effingham County community,” July 22, 2026.
  5. OpenAI, “AI Infrastructure That Works for America: Our Compute Campus Policy Blueprint (PDF),” Nov. 2026.
  6. WTOC, “Effingham County residents file damages lawsuit against OpenAI, county officials over Project Camellia,” Nov. 9, 2026.
  7. WTOC, “Effingham County delays vote on OpenAI data center site plan,” Nov. 5, 2026.
  8. WTOC, “Effingham County residents sue county over data center zoning ordinance, demand transparency,” Sept. 3, 2026.
  9. U.S. Senate Daily Press Gallery, “Floor log and schedule (last updated Nov. 12, 2026),” Nov. 12, 2026.
  10. Congressional Record (Senate), “S. Amdt. 6883 to H.R. 2347, the Capito substitute, Section 2107,” Nov. 10, 2026.
  11. Congressional Research Service, “Invoking Cloture in the Senate.”
  12. Louisiana Public Service Commission, “Home page: “November 18, 2026 Revised Agenda (posted 11/10/2026)” and “Supplemental Agenda (posted 11/13/2026).”
  13. Louisiana Public Service Commission, “Agenda, revised: Business and Executive Session, November 18, 2026, 9:00 AM (posted Nov. 10),” Nov. 10, 2026.
  14. Louisiana Public Service Commission, “Supplemental agenda: Business and Executive Session, November 18, 2026, 9:00 AM (posted Nov. 13),” Nov. 13, 2026.
  15. WWNO / Gulf States Newsroom, “Entergy wants their land for Meta’s power lines. They’re suing the regulators approving them,” Nov. 9, 2026.
  16. WRKF, “Entergy says Meta power lines serve ‘public purpose’ in Lincoln Parish land rights lawsuit,” Nov. 12, 2026.
  17. PJM Interconnection, “RPM auction schedule,” Nov. 15, 2026.
  18. Monitoring Analytics, “2026 Quarterly State of the Market Report for PJM: January through September, Section 1, Introduction,” Nov. 12, 2026.
  19. Bloomberg, via Bloomberg Law, “Tech Giants Face More Grid Cost Pressure on Democratic Sweep,” Nov. 14, 2026.