Loudoun Weighs a Pause on Data Centers
Loudoun County, Va., which calls itself home to the world’s largest concentration of data centers, weighs on Tuesday a pause of up to 12 months on data-center decisions.
LEESBURG, Va., Nov. 16 — Loudoun County’s supervisors are to take up a resolution on Tuesday that would pause their decisions on data centers and electrical substations for up to 12 months, in the county that calls itself home to the world’s largest concentration of data centers. It is item 14.m on the agenda of a business meeting that opens at 4 p.m. in Leesburg.
The county calls it a pause, not a moratorium, for a reason. The board took up the idea in September after a legal opinion from the county attorney “indicating that a moratorium on data center approvals is not legal,” the county said. Twelve months is “the maximum allowed by Virginia law,” it said.Legislative ApplicationsRequests that need a vote of the Board of Supervisors, such as the special exception the county now requires of data-center projects. The board’s action “does not impact applications that are subject to administrative processes,” the county said in September.
The agenda puts the resolution in its own words. It is meant “to pause Board consideration of legislative applications for data centers and substations for a period not to exceed 12 months from the date on which the application was first submitted to the Planning Commission,” so that the board can “apply Phase 2 of the Data Centers Standards and Locations ZOAM and CPAM to the application.” “The resolution shall be effective September 15, 2026, and the pause shall not cause an application to become inactive,” the agenda says.Phase 2A rewrite of the county’s comprehensive plan and zoning ordinance for data centers and substations, expected to wrap up in the summer of 2027. In Phase 1, the county says, the board ended by-right development of most data centers, so that new ones need a legislative review with public input.
That clock matters. Virginia law requires action on such applications within a year, and the county’s zoning ordinance starts the year when an application is sent to a Planning Commission hearing, the county explained in September. Developers could keep filing, and their cases could move through the Planning Commission; the board meant to hold its final votes until the rewrite is done, or for up to a year. It could make exceptions for applications “that involve grid reliability” or whose deadline for a decision is about to expire, the county said then.
The item was to be discussed on Oct. 20. The county put it off to this meeting, saying the delay “will allow county staff additional time needed to develop more information that will help inform the Board’s ultimate decision.” The resolution and its two attachments are posted with the agenda, but this paper could not open them, so it has not seen the staff’s recommendation.
Who Pays
The stakes for the county are fiscal: its adopted budget for fiscal 2027 projects $1.3 billion of revenue from data centers, 40 percent of the total budget, according to a county fact sheet. The county says that money has let it lower the real-property tax rate, generally every year, from $1.145 per $100 of assessed value in tax year 2016 to 80.5 cents in tax year 2026, and it warns that “the county cannot become overly dependent on a single revenue source that may evolve in the future.” Computer equipment in data centers is taxed at the general personal-property rate, $4.15 per $100 of assessed value.
The same agenda carries two other items on the industry: a staff response to a board member’s request for a data-center fact sheet and dashboard, and, on the consent agenda, a timeline extension for an application called Ashburn North Substation. Land is still changing hands. Amazon Web Services paid $99.79 million this month for 23 acres on Wade Drive in Loudoun, the site of a shuttered concrete plant, where it aims to build a 100-foot-tall data center, DCD reported, citing the Washington Business Journal.
The Week’s Other Votes
In Washington, the Senate is to vote on Monday on cloture on the Capito substitute, amendment No. 6883 to H.R. 2347, the vehicle for the permitting bill, after a judicial-confirmation vote, in a series of two votes beginning at 5:30 p.m., according to the Senate Press Gallery. Cloture takes 60 votes, as this paper reported last week. The bill would streamline approvals for power plants, transmission lines and mines “while requiring large data centers to shoulder more of the costs of grid upgrades needed to serve them,” Reuters reported.
House Democrats are already working on changes, Reuters reported on Saturday, while some want to wait until their party takes control of both chambers in January; the Associated Press declared that Democrats had won control of Congress in the midterm elections. “There’s a lot of work behind the scenes right now to improve it,” Representative Kathy Castor, a Florida Democrat, told Reuters. Representative Veronica Escobar, a Texas Democrat, sees less hurry. “It’s not like if we don’t pass something now, it won’t ever get done,” she told Reuters.
It’s not like if we don’t pass something now, it won’t ever get done.
Closer to the ground, the mayor and council of Dalton, Ga., take up a 180-day moratorium on new data centers at 6 p.m. on Monday, the Dalton Daily Citizen reported. It would halt the acceptance and approval of applications not submitted before 5 p.m. that day, and would exempt existing and approved facilities and projects with legally vested rights, the paper said.
On Tuesday, as Loudoun meets, Georgia’s Effingham County takes up its own pause, one that exempts OpenAI’s Project Camellia by name.
Sources
- Loudoun County Board of Supervisors, “Business Meeting Agenda, Tuesday, November 17, 2026, 4:00 PM (item 14.m, Resolution to Pause Board of Supervisors Consideration of Legislative Applications for Data Centers and Substations; items 10.a, 10.b and 14.d.3),” Nov. 2026.
- Loudoun County, “Board Approves Process that Could Pause Legislative Data Center & Substation Applications,” Sept. 17, 2026.
- Loudoun County, “Board of Supervisors to Defer Discussion of Proposed Pause on Some Data Center Applications,” Oct. 2026.
- Loudoun County, “Data Centers in Loudoun County.”
- Loudoun County, “Data Centers in Loudoun County (fact sheet, 2026),” 2026.
- Loudoun County, “Data Centers: Tax Revenues & County Budget.”
- DCD (DatacenterDynamics), “AWS breaks ground on $7bn data center in Indiana,” Nov. 2026.
- U.S. Senate Press Gallery, “Floor log (Senate Daily Press), Thursday, November 12, 2026, and schedule for Monday, November 16,” Nov. 12, 2026.
- The Associated Press, “Calling control of Congress in the 2026 midterm elections.”
- Reuters (via U.S. News & World Report), “As Democrats Seek Changes to Bill on Energy Permits, Divisions Emerge,” Nov. 14, 2026.
- Dalton Daily Citizen, “On the Agenda | Week of Nov. 16,” Nov. 15, 2026.